Following a significant flood event that impacted the building’s basement plant room and main switch room, Pro Mechanical Electrical was engaged to undertake initial BMS rectification works and provide a comprehensive damage assessment.
Pro Mechanical Electrical completed a comprehensive Building Plant Operation Report and fully restored BMS-controlled systems — all within a demanding one-week deadline.
Working closely with the client, services manager, building manager, and Ramsay Health, the team also delivered a complete MSSB upgrade. The new switchboard was designed, built, installed, and commissioned in just six weeks. This project highlights a responsive, solutions-driven approach to complex building services challenges.